The operator of a Shinkansen bullet train service in northeastern Japan says it will resume operations along its entire rail line on April 14. Trains have not been running along some sections since a strong earthquake hit the region last month.
Some segments of the Tohoku Shinkansen line connecting Tokyo and northeastern Japan were damaged and a train was derailed by the magnitude 7.4 earthquake on March 16.
Services have been restored in stages, but there are still no trains running between Sendai and Fukushima stations.
East Japan Railway Company, or JR East, initially planned to resume full operations around April 20.
But the company moved the target forward in light of good progress in reconstruction work.
JR East says it will run 80 to 90 percent of the usual number of trains at first. Trains will run at slower speeds than usual on some sections.
It also says normal operations will resume in early May or later.
Some segments of the Tohoku Shinkansen line connecting Tokyo and northeastern Japan were damaged and a train was derailed by the magnitude 7.4 earthquake on March 16.
Services have been restored in stages, but there are still no trains running between Sendai and Fukushima stations.
East Japan Railway Company, or JR East, initially planned to resume full operations around April 20.
But the company moved the target forward in light of good progress in reconstruction work.
JR East says it will run 80 to 90 percent of the usual number of trains at first. Trains will run at slower speeds than usual on some sections.
It also says normal operations will resume in early May or later.
Similar Readings (5 items)
Quake-damaged Tohoku Shinkansen line resumes full operations
Tohoku Shinkansen will return to normal schedule on May 13
Another section of Tohoku Shinkansen line resumes services after March quake
Tokaido Shinkansen back on track
Most shinkansen service resumes on Wednesday
Summary
Shinkansen bullet train service in northeastern Japan resumes along entire line on April 14, after being disrupted by a magnitude 7.4 earthquake on March 16. Some sections were damaged and a train was derailed. Restoration of services has been gradual but full operations between Sendai and
Statistics
158
Words1
Read CountDetails
ID: 62578fa0-0094-4838-8cc1-77fcc0a80b98
Category ID: nhk
URL: https://www3.nhk.or.jp/nhkworld/en/news/20220405_41/
Date: April 5, 2022
Created: 2022/04/14 12:06
Updated: 2025/12/09 16:59
Last Read: 2022/04/14 12:06